Keller Geotechnique, installed over 4900 soil nails over a 11.5 mile stretch for the major M1 widening scheme between junctions 25 & 28 near Nottingham.
Groundwater was flowing into an underpass section of new road from the junction of two secant piled walls.
As part of the design and construction of a new slip road of the M11 at Stansted Airport, May Gurney Construction Ltd required the design of a series of retaini
Keller Geotechnique has used for the first time, a system of fibre optics developed in conjunction with Cambridge University, to measure the strain developed in soil nail installat
As part of the construction of a new combined retail, office and residential building, the formation of a cutting was required into the existing hillside. The
At two locations on the M4, embankments required steepening to 60 degrees to allow construction of the settlement ponds.
East Midlands Parkway station at Ratcliffe on Soar, was built entirely beside the live Midland Mainline, which links Sheffield with London
Keller Geotechnique were appointed by Osborne ltd to install 276 piles for the Network Rail development, comprising a new Multi storey car park at Luton Railway Station.
The collapse of the ground surface into historic Chalk workings led to the closure of the A2, a major road into London.
As part of the upgrade of the eastern abutment at Turner Rise Railway Bridge, Jackson Civil Engineering Ltd were planning to install jacked reinforced concrete
As part of the flood defences between Maidenhead and Windsor a new channel was being constructed to supplement the River Thames’ capacity. This involved many r
As part of the design and construction of a new road embankment, Carillion Construction Ltd required the design of a temporary retaining wall. KGE proposed the
The nature of the ground conditions and very restricted working space called for a novel approach to installing a hydraulic in-ground barrier and leachate colle
Newport City Council was proposing an extension to the Dockways Landfill Site in Newport. However due to the soft sub grade soils they required improvement of
As a part of construction of a new Foul Pumping Station at Thamesmead, London ground improvement was required to allow a new sewer to be constructed through a b
Systems Geotechnique use revolutionary Glass fibre flat bar anchors to support sheet pile wall.